Morti, Kuna de Wargandi Comarca, Darién Province, Panama
As a community with several existing resources that just don’t fit together correctly, Morti shows great need and promise for a permanent solution. The community has shown a great knowledge of the need for and desire for a water system. The people consider the project a worthwhile investment. The existing Water Committee is an excellent indicator of sustainability and will be worked with as closely as possible during the project.
Solea Water salvaged and utilized as much as possible of Mortí’s existing water system. Through simple miscellaneous small repairs, as well as a new pump and generator, the existing water system is up and running again. The technical support and skilled labor Solea Water was able to provide, as well as the sufficient generator for the entire water system, supplied the Mortí community with clean, drinkable water.
Population: 1000
Local Partners: Benjamin Goodman
Project Costs: $5000
pROJECT: rEPAIR AND REMODEL OF EXISTING WATER SYSTEM
phase 1
July 2015 - September 2015
Construction & procurement of materials
Milestone 1: rehab completion
Progress Point: programs planned & project logistics finalized
phase 2
September 2015 - January 2015
Monitor for effective maintenance
Ensure water committee is functioning properly
Conduct WASH education
Conduct water testing to ensure proper water quality is achieved
Milestone 2: 6 months of water provided through the end of the year